Summer Work Team Schedule for 2015

June 18 to Sometime in late July or Early August – Gary and Cathy Owens (Two Team Members) Insulation and Interior trim. Also finishing the priming of the exterior and maybe add skirting.

July 6 to July 26 The Soldotna Team to finish the Drywall installation.

July 11 to 19 The Weidlers are on vacation.

July 19 to July 26 – The Tuggy Team from Missouri and beyond (Seven Team Members) to install kitchen and bath cabinetry.

August 11 to August 18 - Roger and Cherie DeYoung and Don Ramberg from Harris, Minnesota final detail work.
 